What the work should include
Reading the walls before opening them
A careful contractor scans the bathroom and the rooms around it with a pinless meter and a thermal camera, then confirms with pin readings. Cuts go where the numbers are wet and stop where they aren't, so a two-foot problem doesn't become a whole-wall demolition.
Containment
The bathroom door or the affected section is sealed with plastic and held under negative pressure with HEPA air filtration. The set-up should be sized to the area, as EPA's remediation guidance describes: limited containment for about 10 to 100 square feet, full containment above that (EPA remediation guide, chapter 3).
Removal and cleaning
Wet, moldy drywall and insulation come out and are bagged inside the enclosure. Studs, plates and the back of the tub surround are HEPA-vacuumed and cleaned. Tile backer that has failed is flagged for replacement.
Fixing the water
The leak gets repaired by a plumber, the caulk is cut out and redone properly, or the fan is replaced, resized or re-ducted to an outdoor cap. The written scope should name which applies and who does it.
Drying and rebuild
The cavity dries to normal readings before new drywall or backer goes on, then paint, trim and caulk finish it.